Residential Pavement, Phase A, City Project Nos. 2516, 2517, 2561, 2562 & 2563

To keep community members updated about Project Map
the status of Concord's Residential Pavement, Phase A, City Project Nos. 2516, 2517, 2561, 2562 & 2563. Construction is expected to begin in July 2023.

City staff will update this page regularly with news and photos. 

Have questions? Please contact our Engineering staff.


CONTRACTOR INFORMATION:

Primary Contractor

McGuire and Hester


SEPTEMBER 20, 2023

This week concrete work continues this month in Residential Zone 2B and 2E (Project No. 2517) in preparation for pavement work in October.  A concrete pour on Crestwood Court is scheduled for Wednesday and in Bishop Estate Neighborhood along Adams Drive.IMG_1956-sq

Concrete work in Residential Zone 4Q (Project No. 2562) on Cowell Road (between Galindo Street/Monument Boulevard and Almendra Court) is expected next week.  Paving on Cowell Road is deferred and will be done with paving at Residential Zone 2B and 2E (Project No. 2517). 

See the Project Summary Update for more details. Dates are subject to change depending on the contractor’s progress.


SEPTEMBER 18, 2023

This week pavement rehabilitation is complete in the residential streets of Residential Zone 4Q (Project No. 2562) with Camara Circle and Alemedra Court completed on Monday, September 11.  The contractor is working on adjusting the irons to grade.  Paving on Cowell Road is deferred and will be done with paving at Residential Zone 2B and 2E (Project No. 2517). 

IMG_1867-SQ

 Concrete work continues this month in Residential Zone 2B and 2E (Project No. 2517) in preparation for pavement work in early October.

Location Map

IMG_1876-SQ

See the Project Summary Update for more details. Dates are subject to change depending on the contractor’s progress.


September 7, 2023

This week pavement rehabilitation continues in Residential Zone 4Q (Project No. 2562) and will focus on Marilyn Way, Francine Court, and Systron Drive residential streets. Next week (Monday, September 11) paving will be on Camara Circle.

In Residential Zone 5L (Project No. 2563) utilities are being adjusted to grade on Grant Street in front of Mt. Diablo High School on Saturday, September 9th with pavement marking and signs to be installed in the next week or so.IMG_1702-sqConcrete work continues this month in Residential Zone 2B and 2E (Project No. 2517) in preparation for pavement work later in the month.

See the Project Summary Update for more details. Dates are subject to change depending on the contractor’s progress.


AUGUST 30, 2023

This week pavement activities began in Residential Zone 4Q (Project No. 2562).  This week paving will focus on residential streets Lynn Avenue, Todd Avenue, and Cross Way. Next week paving will be on Marilyn Way, Francine Court, Camara Circle, Systron Drive.

IMG_1689-crop

Concrete work continues this week and the rest of September in Residential Zone 2B and 2E (Project No. 2517).

In Residential Zone 5L (Project No. 2563) utilities are being adjusted to grade in the street (complete by September 8) and pavement marking and signs are to be installed in the next week or so.

See the Project Summary Update for more details. Dates are subject to change depending on the contractor’s progress.


AUGUST 23, 2023

Concrete work has begun this week in Residential Zone 2B and 2E (Project No. 2517).  Pavement work is expected in September.  See the below map for streets in Residential Zone 2B and 2E.

 


Concrete work continues this week and the rest of the month in Residential Zone 4Q (Project No. 2562).  Streets in this neighborhood include Marily Way, Almendra Court, Lynn Avenue, Todd Avenue, Camara Circle, Cowell Road (Galindo to Almendra), and others.  Pavement work in the residential streets is expected to start next week starting with Todd/Lynn and Marilyn Way/Court. 

See the Project Summary Update for more details. Dates are subject to change depending on the contractor’s progress.


AUGUST 17, 2023

The remaining paving in Residential Zone 5L (Project No. 2563) was completed between August 14 and August 16 with a pavement overlay and mill-and-overlay on Gill Drive (from Grant Street to Fredrick Street), Mildred Street, and Karren Street.  The Contractor will install pavement markings and adjust utilities to grade within the month.

 

 

In preparation for pavement overlay in a few weeks, Concrete work continues this week and the rest of the month in Residential Zone 4Q (Project No. 2562).  Streets in this neighborhood include Marily Way, Almendra Court, Lynn Avenue, Todd Avenue, Camara Circle, Cowell Road (Galindo to Almendra), and others.

 

See the Project Update Summaryfor more details. Dates are subject to change depending on the contractor’s progress of work.


AUGUST 10, 2023

Construction continues in Residential Zone 5L (Project No. 2563) and began in Residential Zone 4Q (Project No. 2562).  See the below map for streets in Residential Zone 4Q with construction.  McGuire and Hester continue to work on proposed concrete improvements, which include curbs, gutters, valley gutter, and curb ramps. Base repairs and crack sealing to the streets were made as well.

Please note, paving is expected to start next week from August 14th to 16th Residential Zone 5L. See the below map. This will complete the paving in the neighborhood.
See the Project Update Summary for more details.  Dates are subject to change depending on the contractor’s progress of work.


August 2, 2023

Pavement rehabilitation activities continue, for the Residential Pavement, Phase A Project (Project Nos. 2516, 2517, 2561, 2562, & 2563) within Residential Zone 5L (Project No. 2563) and Mt. Diablo High School.

Paving Plan 2023-08-02

See the Project Update Summary for more details.  Dates are subject to change depending on the contractor’s progress of work.

 IMG_1255


July 26, 2023

Pavement rehabilitation activities began on July 25, 2023, for the Residential Pavement, Phase A Project (Project Nos. 2516, 2517, 2561, 2562, & 2563) within Residential Zone 5L (Project No. 2563) and Mt. Diablo High School.  Impact on the school will be minimalized as the school is not in session with classes starting on August 10th.

A contractor started work on Gill Drive and will work on Grant Street at Mt. Diablo High School this week.


Res Pv 7-26

 

See the Project Update Summary for more details.  Dates are subject to change depending on the contractor’s progress of work.

 

The City appreciates everyone’s patience and understanding.


MaP v2


July 20, 2023

Concrete work continues in Residential Pavement Phase A. See the Project Update Summary for more details.


Image 2


July 13, 2023

Construction activities began on July 10, 2023, for the Residential Pavement, Phase A Project (Project Nos. 2516, 2517, 2561, 2562, & 2563). The projects will rehabilitate pavement in six residential neighborhoods starting with Residential Zone 5L (Project No. 2563) located North of Mt. Diablo High School and west of Grant Street.  See below the location map for Residential Zone 5L.

 

Res Ph A - Location Map 1


The Project involves pavement maintenance and repairs, installing curb ramps at intersections to meet accessibility standards, curb and gutter repairs, water pollution control, traffic control, potholing, utility cover adjustments, and restriping.

See the Project Update Summary for more details.

The project is anticipated to be completed at the end of February (weather permitting).